Renovation of Rietstrasse, section from Rötlistrasse to Rietsporthalle, Benken

Official title in German: Sanierung Rietstrasse, Abschnitt Rötlistrasse bis Rietsporthalle, Benken

Key points at a glanceAI summary

Marty Ingenieure AG is procuring road, drainage and public-lighting works to renew the deteriorated Rietstrasse, where uneven settlement causes ponding, and improve drainage.

Deliverables
Replace the road surface and edge restraints throughout; renew drainage infrastructure and lighting in sections.
Eligibility
Submit three comparable company references from the last 10 years and two each for the proposed site manager and foreman.
Award
Award: offer price 70%, company and personnel references 20%, construction programme and technical report 10%.
Watch out
The offer remains binding for 6 months; execution depends on municipal, landowner and operator approvals.

Documents for your bid

  • 10786_Ausschreibungsunterlagen.zipTender documents · 16.0 MB

Download the documents

Create your free Sealio account: download the documents of this tender and see thousands of other tenders from all over Switzerland.

Key dates

  1. 17.10.2026Published on simap.ch
  2. 02.11.2026Questions round
  3. 16.11.2026, 10:00Submission deadlineDeadline in 19 days

The full analysis of this tender

Detailed scope

A structured view of services, requirements and deadlines.

Buyer review

Context on the procurement and the published information.

Is this tender a fit for your company?

Book a demo and we will walk through this tender with your company profile.

  • Detailed match against your company profile
  • Reasoned go / no-go recommendation
  • Help drafting your bid

Notice text

View on simap.ch

Unofficial reproduction. The German text below is taken unchanged from SIMAP notice no. 45739. Only the official notice is binding.

Die Rietstrasse in Benken ist im Abschnitt der Rietstrasse 5 – 18 in einem schlechten Zustand und muss saniert werden. Bei diversen Strassenbereichen gibt es stehendes Regenabwasser, da die Strasse gegenüber den Strassenabläufen unterschiedlich gesetzt hat. Die Randabschlüsse und der Belag sollen im gesamten Projektperimeter komplett ersetzt werden. Weiter soll in einem Abschnitt die öffentliche Beleuchtung erneuert werden.