Accepting bidsDeadline in 17 daysSupporting walls

Peist - Langwies, km 17.400, Palätsch gravity wall

Official title in German: Peist - Langwies, km 17.400, Schwergewichtsmauer Palätsch

Key points at a glanceAI summary

Rhätische Bahn AG is replacing a badly damaged, roughly 30 m historic stone railway retaining wall to secure long-term track stability.

Deliverables
Demolish the wall and build a roughly 31 m in-situ concrete gravity wall, with drainage and backfill.
Contract
Single-unit-price works contract; fixed prices and monthly progress payments, generally payable within 45 days.
Eligibility
Lead contractor needs two comparable works of at least CHF 400'000 each; foreman needs one, within 10 years.
Award
Price and additional-cost risk weigh 50%; provider and bid quality each weigh 25%.
Watch out
Offers bind for 6 months; the contractor bears work-related damage liability and provides a 2-year guarantee bond.

Documents for your bid

  • 2408 - Submissionsunterlagen.zipTender documents · 44.6 MB

Download the documents

Create your free Sealio account: download the documents of this tender and see thousands of other tenders from all over Switzerland.

Key dates

  1. 16.10.2026Published on simap.ch
  2. 28.10.2026Questions round
  3. 13.11.2026, 23:59Submission deadlineDeadline in 17 days
  4. 18.11.2026, 10:00Bid opening

The full analysis of this tender

Detailed scope

A structured view of services, requirements and deadlines.

Buyer review

Context on the procurement and the published information.

Is this tender a fit for your company?

Book a demo and we will walk through this tender with your company profile.

  • Detailed match against your company profile
  • Reasoned go / no-go recommendation
  • Help drafting your bid

Notice text

View on simap.ch

Unofficial reproduction. The German text below is taken unchanged from SIMAP notice no. 45919. Only the official notice is binding.

Die rund 30 m lange Natursteinmauer aus der Zeit des Bahnbaus weist erhebliche Schäden (Zustandsklasse 4) auf und muss zur Gewährleistung der langfristigen Stabilität des Bahntrassees ersetzt werden. Vorgesehen ist der Rückbau der bestehenden Mauer und der Neubau einer ca. 31 m langen Schwergewichtsmauer in Ortbeton inklusive Entwässerung, Hinterfüllung und Anpassung der talseitigen Bankettsicherung.

Get started

Ready to win more work?

Bring a live RFP. We'll show you how Sealio handles it in less than 10 seconds.