V1502 EV Enge Seewasserleitungen
Elektrizitätswerk der Stadt Zürich (ewz) is procuring intake and return lake-water pipelines for the Energieverbund Enge pumping station to route lake water through heat exchangers.
- Deliverables
- The intake pipeline is 490 m and the return pipeline 480 m, extending along the lakebed to their respective points.
Key dates
- 20.08.2026Published on simap.ch
- 23.09.2026Questions round
- 15.10.2026, 12:00Submission deadline
The full analysis of this tender
Detailed scope
A structured view of services, requirements and deadlines.
Buyer review
Context on the procurement and the published information.
This tender is closed
Book a demo to see how Sealio finds the next similar tenders for your company.
- Detailed match against your company profile
- Go / no-go recommendation
- Help drafting your bid
Notice text
View on simap.ch
Unofficial reproduction. The German text below is taken unchanged from SIMAP notice no. 42621. Only the official notice is binding.
Im Rahmen der vorliegenden Submission werden die Seewasserfassungs- und Rückga-beleitung für die Seewasser-Pumpstation des Energieverbund Enge ausgeschrieben. Das Seewasser wird über die Fassungsleitung in einer Tiefe von 15 m gefasst. Es fliesst geodätisch in den Pumpenkeller, wo es durch die Wärmetauscher geführt wird und danach über die Rückgabeleitung zurück in den See gepumpt wird. Die beiden Leitungen verlaufen unterirdisch vom Pumpenkeller rechtwinklig zum Seeufer-verlauf bis in eine Tiefe von ca. 12 m. Dort treten sie aus dem Untergrund aus und führen auf dem Seegrund bis zur Fassungs- bzw. Rückgabestelle. Die Fassungsleitung hat eine Länge von 490 m; die Rückgabeleitung eine Länge von 480 m. Die Fassungsleitung tritt auf einer Höhe von 403.50 m ü. M. in den Pumpenkeller ein. Die Eintrittshöhe liegt ca. 2.5 m (Rohrmitte) unter dem mittleren Wasserspiegel des Zürichsees.