Award pendingIndustrial machinery

KEZO Replacement WtE Facility

Official title in German: KEZO Ersatzneubau KVA

Key points at a glanceAI summary

Zweckverband Kehrichtverwertung Zürcher Oberland is replacing its waste-to-energy plant with a new 120,000 t/a single-line facility to support waste incineration and energy use.

Deliverables
Three process lots cover grate firing and boiler, flue-gas cleaning, and the water-steam cycle.
Lot 1
Combustion line for 16.5 t/h maximum continuous load; 57.3 MW gross heat capacity.
Lot 2
Flue-gas cleaning for one combustion line, including dry sorption, catalyst and condensation scrubber.
Lot 3
Water-steam cycle for energy recovery, including turbine-generator, air-cooled condenser and heat extraction.

Key dates

  1. 05.05.2026Published on simap.ch
  2. 15.05.2026Questions round
  3. 12.06.2026, 16:00Submission deadline

Lots

LotTitleLocation
1Feuerung und KesselHinwil (ZH)
2RauchgasreinigungHinwil (ZH)
3Wasser - Dampf - KreislaufHinwil (ZH)

The full analysis of this tender

Detailed scope

A structured view of services, requirements and deadlines.

Buyer review

Context on the procurement and the published information.

This tender is closed

Book a demo to see how Sealio finds the next similar tenders for your company.

  • Detailed match against your company profile
  • Go / no-go recommendation
  • Help drafting your bid

Notice text

View on simap.ch

Unofficial reproduction. The German text below is taken unchanged from SIMAP notice no. 36244. Only the official notice is binding.

Das Projekt KEZO 2028 bezeichnet den Ersatzneubau der neuen KVA mit einer Kapazität von 120'000 t/a in einer Linie. Das Projekt besteht unter anderem aus den verfahrenstechnischen Hauptlosen «Feuerung und Kessel (Los 1)», «Rauchgasreinigung (Los 2)» und «Wasser-Dampf-Kreislauf (Los 3)».