Freienstein Power Plant Fish Pass Rehabilitation, Civil Engineering Works
Official title in German: KW Freienstein Sanierung Fischgängigkeit Baumeisterarbeiten
toesStrom AG (Entegra Wasserkraft AG) is replacing the existing fish ladder at Freienstein hydropower plant to restore fish passage.
- Deliverables
- Works include a new reinforced-concrete fish ladder, structures for a new screen and fish descent, and an access road.
- Watch out
- Third-party contractors will work concurrently on the power plant and weir gates.
Key dates
- 19.08.2026Questions round
- 28.08.2026Published on simap.ch (Correction)
- 18.09.2026Questions round
- 16.10.2026, 12:00Submission deadline
- 19.10.2026Bid opening
The full analysis of this tender
Detailed scope
A structured view of services, requirements and deadlines.
Buyer review
Context on the procurement and the published information.
This tender is closed
Book a demo to see how Sealio finds the next similar tenders for your company.
- Detailed match against your company profile
- Go / no-go recommendation
- Help drafting your bid
Notice text
View on simap.ch
Unofficial reproduction. The German text below is taken unchanged from SIMAP notice no. 42000. Only the official notice is binding.
Die Fischgängigkeit beim Kraftwerk Freienstein wird saniert. Dazu wird die bestehende Fischtreppe rückgebaut und durch einen Neubau in Stahlbetonbauweise ersetzt. Weiter werden Stahlbeton-Strukturen für die neuen Rechenanlage und den Fischabstieg erstellt. Für die Erschliessung der Liegenschaft und der Baustelle muss eine Umfahrungsstrasse erstellt werden. Die Baugrubensicherung erfolgt mittels Rühlwand mit Holzausfachung. Fluss- und Teichseitig kommen Big-Bags zum Einsatz. Am Wehr selber finden Betoninstadsetzungsarbeiten, Kolksicherungsmassnahmen und die Sanierung der Prallböden statt. Parallel finden durch Drittunternehmer Arbeiten am Kraftwerk, den Wehrtafeln, etc. statt.