Award pendingDistrict-heating plant construction work

Emergency boiler incl. chimney for the district heating power plant of the Winterthur waste incineration plant

Official title in German: Notheizkessel inkl. Kamin für das Fernheizkraftwerk der Kehrichtverwertungsanlage Winterthur

Key points at a glanceAI summary

Stadtwerk Winterthur is procuring an emergency heating boiler and chimney for its waste incineration plant’s district heating facility, for installation in a planned building extension.

Deliverables
Produce the boiler, burner and chimney; assemble, deliver, install by mobile crane and commission.

Key dates

  1. 12.06.2026Published on simap.ch
  2. 25.06.2026Questions round
  3. 10.08.2026, 12:00Submission deadline

The full analysis of this tender

Detailed scope

A structured view of services, requirements and deadlines.

Buyer review

Context on the procurement and the published information.

This tender is closed

Book a demo to see how Sealio finds the next similar tenders for your company.

  • Detailed match against your company profile
  • Go / no-go recommendation
  • Help drafting your bid

Notice text

View on simap.ch

Unofficial reproduction. The German text below is taken unchanged from SIMAP notice no. 38647. Only the official notice is binding.

Produktion der drei wichtigsten Hauptbestandteile: Kessel, Brenner und Kamin Zusammenstellung der Eizelteile inkl. der dazugehörigen Steuerung Lieferung vor Ort mit Aufstellung / Einbau mittels Pneukran auf das Stahlgerüst in die vorgesehene Gebäudeerweiterung des Fernheizwerks Fertigmontag der einzelnen Teile inkl. Inbetriebnahme weitere Details siehe Dokument SW Teil 4 A in den Ausschreibungsunterlagen